NextDecade continued construction on Phase 1 of the Rio Grande LNG Facility, with significant progress on Trains 1, 2, and 3. The company also announced development plans for additional liquefaction capacity (Trains 6-8) and secured a $175 million senior secured loan to fund working capital and expansion train development.
Overall project completion for Trains 1 and 2 and common facilities reached 38.1%, in line with the EPC contract schedule.
Overall project completion for Train 3 reached 15.3%, also in line with the EPC contract schedule.
Development plans for Trains 6, 7, and 8 were announced, cumulatively increasing total liquefaction capacity by approximately 18 MTPA.
A $175 million senior secured loan was secured, with proceeds used to repay existing borrowings and fund working capital and expansion train development.
NextDecade expects to continue construction on Phase 1, progress Trains 4 and 5 towards positive FIDs, and advance permitting for additional liquefaction capacity (Trains 6-8).