Origin Materials reported strong customer demand and progress on its mission to enable the world’s transition to sustainable materials, completing the installation of the key production modules at Origin 1 six months ahead of schedule and increasing signed offtake agreements and capacity reservations to $4.2 billion.
Completed the installation of the key production modules at Origin 1 six months ahead of the plan.
Increased signed offtake agreements and capacity reservations to $4.2 billion from $3.5 billion in August.
Reaffirmed the Origin 1 capital budget and schedule.
Origin 1 remains on track for completion by the end of 2022.
The Company is maintaining previous guidance for Adjusted EBITDA loss but is updating its capital spending outlook.