PureCycle Technologies announced a delay in the mechanical completion of its Ironton facility to Q1 2023 due to equipment delivery delays. The company finalized a joint venture with SK geo centric for a facility in South Korea. Offtake agreements for Augusta lines 1 and 2 reached 111% of capacity. They are evaluating financing options to fund the Augusta project and East Coast PreP facilities.
Ironton facility mechanical completion and pellet production expected in Q1 2023.
Offtake agreements for Augusta lines 1 and 2 are at 111% of nameplate capacity.
Joint Venture Agreement finalized with SK geo centric for a purification facility in Ulsan, South Korea.
Financing targeted to fund Augusta lines 1 and 2 and three East Coast PreP facilities.
PureCycle anticipates mechanical completion, startup, and full commissioning of Augusta lines 1 and 2 to be in the second half of 2024, with construction activities in Ulsan, South Korea commencing in the second half of 2023, and production ramp-up currently anticipated in the second half of 2025. They expect their three PreP facilities to be fully operational in advance of the completion of Augusta purification lines 1 and 2.